This build started in mid 2020. A dedicated room planned for 35 racks — from bare ground to a clean shell ready for frames.

Each step below is one moment in the build.

1 · Foundation & brick walls

Concrete pillars up, bricks going in, dirt and materials on site. Mid 2020 — the room starts outside the old footprint.

Foundation & brick walls
Foundation & brick walls

2 · Fresh concrete floor

Wet slab poured inside the brick shell. Reflective grey concrete before tile — the base everything else sits on.

Fresh concrete floor
Fresh concrete floor

3 · Tiles & ceiling boards

Gloss floor tiles down, green ceiling boards up, walls still raw. Work light only — finishing has begun.

Tiles & ceiling boards
Tiles & ceiling boards

4 · Paint & drying

KOVA buckets, fans on, final coats. The room turns from construction grey into a clean farm shell.

Paint & drying
Paint & drying

5 · Painted shell & outlets

Walls and ceiling painted light grey. Outlet cutouts along the back wall, scaffold still up for high work.

Painted shell & outlets
Painted shell & outlets

6 · Cabling before racks

Long clean room, cable coils on the floor, fans still running. Space mapped for thirty-five racks — frames come next.

Cabling before racks
Cabling before racks

Custom-made tanks at the farm

While the room went up, the glass was built here too — rimless tanks silicone-cured on the floor, sized for the racks.

7 · Glass panes ready

Stacks of cut glass on mats — raw material before a single tank is stood up.

Glass panes ready
Glass panes ready

8 · Silicone & blue tape

Rimless tanks curing in rows. Blue tape holds every joint while silicone sets.

Silicone & blue tape
Silicone & blue tape

9 · Building on the floor

Custom tanks made at the farm — built one by one on the tile.

Building on the floor
Building on the floor

10 · Workshop full of tanks

Dozens curing at once. Scale for thirty-five racks starts with glass.

Workshop full of tanks
Workshop full of tanks

11 · Finished tanks stacked

Cured, cleaned, stacked — ready for the racks in the new room.

Finished tanks stacked
Finished tanks stacked

Custom racks ready & placed

Frames built and painted, then rolled into the new room — empty shelves waiting for the tanks above.

12 · Racks painted & ready

Custom metal frames finished outdoors — light grey paint, waiting to move in.

Racks painted & ready
Racks painted & ready

13 · First racks in the room

Through the glass door — empty frames standing in the clean shell.

First racks in the room
First racks in the room

14 · Rows filling the room

Parallel aisles of custom racks. Pipe on the floor — plumbing comes next.

Rows filling the room
Rows filling the room

15 · Lights on the racks

Per-tier LED strips live. The room starts to look like a farm before tanks arrive.

Lights on the racks
Lights on the racks

16 · Racks placed & wired

Ladder still in the aisle — frames locked in, lights run, ready for glass.

Racks placed & wired
Racks placed & wired

Air & water system

Racks and tanks only work when air and water reach every cup. This is the plumbing that turns the room into a farm.

17 · Tanks on racks, lines starting

Glass in place. White tubing, PVC bundles, and fittings on the floor — air and water begin.

Tanks on racks, lines starting
Tanks on racks, lines starting

18 · Through the glass — plumbed rows

Looking in from the door: every tier lit, white lines running to empty tanks.

Through the glass — plumbed rows
Through the glass — plumbed rows

19 · Main lines & plant room gear

Aisle view with PVC still on the floor. Reservoir and blower gear taking shape at the far end.

Main lines & plant room gear
Main lines & plant room gear

20 · Air to every tank

White manifolds along each shelf, black airlines dropping in — one feed per tank.

Air to every tank
Air to every tank

21 · Full air & water grid

Valves, airlines, LEDs — the room becomes a system, not just shelves of glass.

Full air & water grid
Full air & water grid

Finished — all tanks stocked

The end of this build chapter: empty shell to a running room. Thirty-five racks planned — tanks stocked, systems live.

22 · Stocked — aisle A

Every tier live. Green water, plants, sponge filters — the room finally doing its job.

Stocked — aisle A
Stocked — aisle A

23 · Stocked — full room

Racks labeled, airlines dialed, tanks full. Mid 2020 build complete as a working farm.

Stocked — full room
Stocked — full room

24 · Stocked — center aisle

Wide view down the middle — every rack lit, tanks green and running. The finished room at full stock.

Stocked — center aisle
Stocked — center aisle

Farm note: A room isn’t finished when the paint dries. It’s finished when every tank holds life and the daily walk feels calm.